Contractor mobilization and site preparation will begin on Monday, August 21 at Providence Village Inc. at 1200 Princess Street. Work will include installation of construction fencing, curb cuts along Princess Street to allow for installation of a construction entrance and exit, top soil removal and installation of granular material to build a construction road.
The week of August 28th, excavation and rock breaking will begin on the west side of the site and move eastward around the south side of Providence Motherhouse for the purpose of installing new site services for the new Providence Manor. Rock excavation will continue through the fall and winter months as the project progresses.
We are working closely in partnership with the Providence Care team. Together, we will provide video and written updates on our website and social media platforms to share information and document the progress.